LTA has started to carry out repair as the first stage of
recovery works. Concrete is being poured into the cracks in some areas at the
perimeter of the incident site. This is to stabilise the ground and to prevent
water seepage. We will carry out these works without affecting SCDF's rescue operations in the area.
The surrounding buildings have been assessed to be safe for
use by the BCA and LTA. LTA is monitoring, and there is no further ground
movements in this area as well as in the area around the Merdeka Bridge and
Crawford Underpass.
Traffic Situation
There is no change to the traffic diversion
plans (See
Annex A).
Traffic along the East Coast Parkway (between Marine Parade
and Rochor Road) is experiencing normal peak hour traffic conditions.
Traffic is also heavy along Kallang Road up to Geylang Road.
We have been monitoring the traffic situation there and adjusted the traffic
signals to cater to the heavier city-bound traffic.
|