New Page 1
The Land Transport Authority (LTA) and
Nishimatsu Construction Co. Ltd/ Lum Chang Building Contractors Pte Ltd Joint
Venture (NLC)1 will
reconstruct the Circle Line (CCL) MRT tunnels between the Millenia and Boulevard
MRT stations along a new alignment, bypassing the area that collapsed. The
collapsed area has debris and obstructions, and NLC has proposed a new alignment
which LTA has accepted. The Nicoll Highway MRT station will also be built
approximately 100 metres south of its original location.
A new set of twin MRT tunnels will be
constructed from the west end of Boulevard MRT station towards Millenia MRT
station. The tunnels, which are approximately 1.8 kilometres long, will cross
under the Kallang Basin and will be about 25 metres deep.
The Nicoll Highway MRT station will now be
sited under Republic Avenue and the adjacent land. The station will have two
entrances: the north entrance will be linked via an overhead bridge to the
Concourse, and the south entrance will serve the park there. Please refer to Annex
A for a map of the new location of the tunnels and station.
Construction Method
The realigned tunnels will be constructed
using the bored tunnelling method 2 while
the new Nicoll Highway MRT station will be built using the top-down construction
method. These methods differ from the cut-and-cover method used 3
to construct the original tunnels and station.
The top-down construction method4
, which will be used to construct the new Nicoll Highway MRT station, involves
the construction of 1.5-metre thick, permanent diaphragm walls up to 60 metres
deep. These diaphragm walls will be socketed into the hard soil strata to
minimise ground movement.
Construction of the new MRT tunnels and
station will start in the middle of 2005, and this stage of the Circle Line
(CCL1) is scheduled to be opened by 2010.
Approach To Managing Reconstruction Works
The NLC project team for the reconstruction
works will be a new team and will comprise professionals with the necessary
expertise and skills to carry out the works. LTA will also have a new project
team and will implement improvements for the reconstruction of the MRT tunnels
and station at Nicoll Highway.
Independent Checks
LTA will engage an independent consultant to
check the design of temporary works prepared by the contractor. The permanent
works will be endorsed by an Accredited Checker, as with the current procedure.
Specialist Instrumentation Contractor
LTA will also appoint a specialist
instrumentation contractor who will report to LTA directly. This will ensure
that there is better control over the proficiency, skill set, experience and
training of instrumentation staff, as well as the responsibilities and duties of
the instrumentation contractor.
Risk Management Process
LTA has a risk register to comprehensively
review the design and construction risks. This has been improved following the
incident by requiring that during construction, all site staff immediately
report instrumentation readings which have been breached to a committee
comprising senior design and project staff for review and follow-up.
__________________________________
1 As
the civil works contractor for the Nicoll Highway and Boulevard MRT stations and
adjacent tunnels, NLC will also be the contractor for the reconstruction of the
MRT tunnels and station at Nicoll Highway.
2 The bored
tunnelling method involves tunnelling underground without having to cut open the
earth. Two Tunnel Boring Machines (TBM) will be sunk into the Launch Shaft up to
the required depth. The TBMs will then bore through from this shaft until they
reach the Receiving Shaft, where they will be dismantled and removed.
3 The
cut-and-cover method involves excavation to the final required depth, while
using retaining walls and struts to support the soil at both sides. When
excavation is completed, the base slab of the underground structure is cast at
the bottom-most level, followed by the side walls. Casting of the concrete
progresses upwards, level by level, until the roof of the structure is
completed.
4 The top-down method
involves installing the diaphragm walls first, followed by the casting the roof
slab of a station. Open excavation will not be too deep as the roof slab, which
is about 6 metres below ground, will be immediately cast once this level is
reached. The roof slabs are thick and will act like solid struts, or support
beams, for the next level of excavation. Excavation continues through openings
in the roof slabs until the station's concourse level is reached and cast. This
process is repeated until the base slab, the deepest part of the station box, is
completed.
|