1. The Land Transport Authority will commence works for the
widening works of the stretch of the CTE between Ang Mo Kio Ave 1 and Ang Mo Kio
Ave 3 from 2 June onwards.
2. The works for this contract will involve the widening of
the section of CTE between Ang Mo Kio Avenue 1 and Ang Mo Kio Avenue 3 from the
existing dual 3-lane carriageway to a dual 4-lane carriageway.
3. A new covered pedestrian overhead bridge with ramps and
link-ways will be constructed as part of the widening works.
4. Works for this stretch of the CTE is scheduled for
completion by end 2009.
5. As with all other land transport infrastructural works, LTA
will be putting in the necessary control measures to ensure that the public will
not be unduly affected by the works. Should there by any road closures required,
directional and information signs will be placed way in advance of the road
closure to inform and guide motorists of the alternative routes.
6. This is the first stretch of the comprehensive widening and
improvement works to the CTE, announced earlier this year.
7. Three more stretches of the existing CTE will be widened to
provide 4 continuous traffic lanes between the Pan Island Expressway (PIE) and
Yio Chu Kang Road by end 2011. The Land Transport Authority will be calling
contracts to widen these three stretches by the end of the year.
8. "We are pleased to share that the first phase of the
CTE widening project has kicked off and this will bring about benefits to the
residents living along the North-East corridor when the widening project is
completed," said LTA Chief Executive, Mr Yam Ah Mee.
|