New Page 1
1. The new vehicular interchange between the Pan-Island Expressway (PIE) and
Bedok North Avenue 3 will be opened to traffic on 29 November 2008 from 4pm
onwards.
2. Works for the latest road interchange with the PIE began in June 2006 and
involved the construction of four slip roads to connect Bedok North Avenue 3 to
the PIE. This also involved works to widen Bedok North Avenue 3 from two lanes
to three lanes in both directions.
3. As part of the improvement works, LTA has also constructed two new
pedestrian overhead bridges across Bedok North Avenue 3, provided ramps to the
existing pedestrian overhead bridge across the PIE and upgraded five bus
shelters along Bedok North Avenue 3 and Bedok Reservoir Road. The entire
upgrading project was completed at a cost of $20.5 million.
4. Please refer to Annex
A for the location map and scope of works.
5. With the opening of this vehicular interchange, motorists, especially
residents in the Bedok North Estate, will be able to enjoy a direct and faster
connection between Bedok North Avenue 3 and the PIE. The new interchange will
also serve as an alternative to the two existing interchanges with the PIE at
Bedok North and Simei.
|