To facilitate the construction of Stage 2 of
Circle Line, the following roads will be realigned:
Hougang Avenue 3
A stretch of Hougang Avenue 3, near the
junction of Kim Chuan Road and Hougang Avenue 3, will be realigned on Monday,
10 November 2003.
Two lanes along Hougang Avenue 3, in the
direction of Hougang, will be closed on Saturday, 8 November 2003 at
2.00pm. Two lanes along Hougang Avenue 3, in the direction of Eunos, will
also be closed on Sunday, 9 November 2003 at 2.00pm. For
both lane closures, the remaining one lane will be closed only after works on
the first two lanes are completed and traffic is diverted to the new lanes.
This realignment will be in place until the
third quarter of 2005.
Paya Lebar Road
A stretch of Paya Lebar Road, between Circuit
Link and BP Petrol Kiosk, will be realigned on Saturday, 8 November 2003 at
8.00pm. The pedestrian walkway will also be realigned accordingly. This
realignment will be in place for about two months.
A stretch of Paya Lebar Road, from Sims Avenue
to Paya Lebar MRT station, will also be realigned on Sunday, 9 November 2003
at 5.00am. This will be in place until the third quarter of 2004.
Motorists are advised to drive carefully and
follow the directional signs displayed.
Maps are attached for your reference.